Sixteen lit letters, each about 6 ft tall, across the top of a 12-level car park beside Pune station. Scaffold climbs, a board meeting, 2,105 LEDs, no lift and a 300 mm RCC wall: here’s how it went up.

JEHANGIR HOSPITAL in 6 ft lit letters along the top of the hospital’s multi-level car park on Sassoon Road, Pune, by day

Behind the scenes · Jehangir Hospital, Pune

One of the first signs you see as your train pulls into Pune

Jehangir Hospital, on Sassoon Road, has built a new multi-level car park right beside Pune station. Since February 2026, its top carries the hospital’s name in lit letters, each about as tall as a grown man.

Trains pulling into the station run right past it. For many people arriving in Pune, it is one of the first signs they see. For us it is one of the biggest jobs we have ever done, and a huge feather in our cap. This is the story of how it went up.

Each letter

About 6 ft tall

The sign

91 ft long, on a 98 ft wall

The light

2,105 Osram LED modules

The way up

12 parking levels, no lift

The car park tower at dusk with the JEHANGIR HOSPITAL sky sign glowing on top

The building

A name on the skyline, by the railway tracks

The car park is a tall concrete building with a parapet wall running around its top. The hospital wanted two signs on it: the English name on the face that looks towards the station and the tracks, and the Marathi name, जहांगीर हॉस्पिटल, on the other face.

The English sign is the one you see here. The Marathi sign is ordered and will go up later this year.

Timeline of the Jehangir Hospital sky sign job, from the first look in February 2025 to the engineer’s report in March 2026 (illustration)

How the job ran, from the first look in February 2025 to the engineer’s report in March 2026.

Feb 2025: the car park still being built, seen from the hospital’s roof, with bare rebar at the top

Before there was a wall

Up an unfinished building, on foot

Our first look at the building was in February 2025, from the roof of the hospital next door. The car park was still rising, with bare steel rebar sticking out of its top and green safety net around it.

To plan a sign, you have to stand where it will go. So, while the building was still under construction, we went up. There was no lift: just scaffold stairs, plank walkways and a long way down. Hard hats on and safety harnesses tied, we climbed past the rebar cage where the parapet wall would later be cast. Sachin from our team led the way; I filmed every step, and my knees remember every one of them.

July 2025

Where eagles dare

These were shot on the way up. The green net is the only thing between the planks and the drop.

Jul 2025: Sachin from our team on scaffold planks beside the bare rebar of the future parapet

On the planks

Sachin on the scaffold walkway beside the bare rebar of the future parapet.

Jul 2025: looking down the scaffold stairs on the way up the unfinished building

Looking down

The scaffold stairs, looking down from near the top.

Real photos from our climb, 10 July 2025.

Nov 2025: Sachin on the finished terrace at sunset, before the letters went up

Back on top

The view the letters would face

By November 2025 the terrace was finished, with a walkway and railing in front of the parapet wall. Sachin went back up with a hard hat on, and we stood where the letters would go.

That walkway would matter later: it meant we could stand behind the wall and fix the letters by hand, with no gondola.

The height

A long way down

Two views from the top: one over the safety net in July, one from the finished terrace in November, straight down onto the tracks.

July 2025: looking down past the green safety net from the top of the unfinished Jehangir Hospital car park

July 2025

Over the safety net, straight down onto the roofs below.

November 2025: from the car park terrace, straight down onto the railway tracks beside Pune station

November 2025

From the terrace, straight down onto the railway tracks by Pune station.

Real photos, taken by our team.

The board meeting

Two sample letters, and a lot of questions

In late 2025 I was called to present to the hospital’s board of directors and trustees: how I planned to put the letters up, and what they would be made of.

I didn’t want to go in with just slides. So we made two sample letters in exactly the build we were proposing: an English J and a Marathi ज, with the same aluminium, the same LEDs and the same acrylic face as the real thing.

The questions came from every side of the table. How long will it take? How long will it last? What maintenance does it need? What are the chances of it failing? We answered them one by one, with the samples on the table.

At the end of the meeting the board ordered not one but two signs: the English name for one face of the car park, and the Marathi name for the other.

The proposal

Planned on a photo of the building, by day and by night

In the end the hospital chose letters only, in white, about 6 ft tall, in a single 91 ft line on the 98 ft wall.

Our proposal: day and night mock-up of the letters on the building (early option with a logo)

Early proposal mock-up: day and night views of one layout on the building (this option had a logo; the final sign is letters only).

Our proposal: how the sign would look from the Pune station side (early mock-up)

Early proposal mock-up: how the sign would read from the station side.

On paper

Sizes and the wall we had

The architect’s drawings marked the top band of the car park as the area for branding. Our dimension slide fitted the letters to it: English letters 71.77 inches (about 6 ft) tall, in a line 1,094 inches (about 91 ft) long, on a wall 30 m (98 ft) wide.

Our proposal: dimensions of the English and Marathi signs

From our proposal: the dimensions of the English and Marathi signs.

The architect’s front and rear elevations of the Jehangir Hospital car park, with the area for branding at the top

The architect’s front and rear elevations, with the area for branding at the top.

Inside a letter: rows of LED modules in a zigzag across the tray

The letters

Built to stay up for decades

Each letter is a hollow box of 3 mm aluminium, 4 inches deep, riveted together. Aluminium doesn’t rust, so it can take years of monsoon and summer sun at that height.

Inside, outdoor-grade Osram LED modules are packed tightly across the back of each letter, so the whole face glows bright and even, with no dark patches.

How one letter is built and fixed: aluminium body, trim cap, acrylic face, LEDs and chemical anchors (illustration)

Illustration: one letter cut through, and how it is fixed to the wall. Not to scale.

A letter switched on in our workshop for testing

In our workshop

Twenty-odd days on the workshop floor

Our floor is never empty. If you look closely at these photos you’ll spot other jobs in progress around the giant letters: a clinic’s banner, a stencil, a round backlit panel. That’s a normal day at Orchid.

Scale

Letters taller than the team

The letter O standing taller than a man in our workshop, ready to be wrapped

The O

The letter O standing on its edge, taller than a man.

Giant sky sign letters with their LEDs laid out across the Orchid Digitals workshop floor

The floor

Letters laid out across the workshop floor, LEDs in.

Real photos from our workshop, February 2026.

Close-up of a soldered joint sealed in black heat-shrink sleeve inside one of the letters

The detail most people never see

Every joint soldered and sealed

Most sign makers twist the wires of a joint together and wrap them in insulation tape. It works on day one. Over time the tape dries and lifts, the twist loosens, the copper blackens, and the letters start to dim or flicker. On a sky sign, that joint is out of reach.

We go the extra mile. Every joint is soldered, so the strands fuse into one wire, then sealed in a heat-shrink sleeve that shrinks tight around it. No air, no water, no carbon, no sparks. We do this on every board we make, not just the big ones.

A twisted-and-taped wire joint next to a soldered, heat-shrink-sealed joint (illustration)

Illustration: a twisted-and-taped joint next to a soldered, heat-shrink-sealed joint. Not to scale.

Close up

Solder and sleeve

Soldering the LED module chains inside a letter

In the workshop

The soldering iron and the LED module chains inside a letter.

Soldered joints sealed in black heat-shrink sleeves on the feed wires inside a letter

On the wall

Black heat-shrink sleeves on the joints of the feed wires.

Real photos from the job.

Before it was built

What will it cost to run? We worked it out

A sign this size uses real electricity, and the hospital wanted to plan its running cost. Most sign quotes stop at the price of the board. We went further.

We counted every LED module in our letters, 2,105 of them at 1.8 W each, added 10% for losses in the long cable run from the foot of the building, and worked out the load: about 4.2 kW. Lit from 6 pm to midnight, that’s about 25 units of electricity a night. With that, the hospital could plan for the daily running of the sign before a single letter was made.

The load sum for the Jehangir sign: 2,105 LED modules at 1.8 W, about 4.2 kW, about 25 units a night (illustration)

The load sheet we made for the hospital, redrawn. 1 unit = 1 kWh.

A finished letter wrapped in bubble wrap and corrugated sheet for the trip

Still no lift

Sixteen 6 ft letters, up 12 levels by hand

Each finished letter was wrapped in bubble wrap and corrugated sheet and loaded onto a truck. At the car park there was still no lift to the top.

So on 26 February 2026 our team and porters carried every letter up the stairs to the terrace, one at a time,. Seven or eight porters did the carrying; Sachin, the team and I went up with them.

26 February 2026

Truck to terrace

A wrapped letter being unloaded from the truck at the Jehangir Hospital car park

Unloading

A wrapped letter coming off the truck at the car park.

Carrying a wrapped letter up the stairs: there was no lift to the top

The stairs

Carrying a letter up the staircase: there was no lift.

Real photos from the day.

Mitesh Sanghani unpacking a letter face on the terrace on a hot installation day

Hands on

One of the rare times I fixed letters myself

Usually I’m the one talking to the client. Not this time. Up on the terrace it was so hot that I ended up in shorts with my T-shirt off, unpacking faces and fixing letters alongside the team.

The wrapped letters stood in a row along the wall, ready to go up.

The wrapped sky sign letters lined up along the terrace wall before fixing

The wrapped letters lined up on the terrace before fixing.

Drilling the RCC parapet for the chemical anchors behind the letter R

The fixing

Straight into 300 mm of solid RCC

On many towers, the wall at the top is made of concrete blocks. Screws don’t hold well in blocks, so we first bolt a steel frame into the building’s beams and fix the letters to the frame.

Here the parapet is solid RCC, 300 mm thick, right through. So no frame was needed: each letter is fixed directly into the wall with chemical anchors, threaded studs set in resin inside drilled holes, which hold far better than ordinary screws.

And because there is a walkway behind the parapet, we stood on it and worked by hand. No gondola either.

1

Mark and drill

Mark each letter’s position on the RCC wall and drill the anchor holes.

2

Set the anchors

Set threaded studs in resin in each hole and let them cure.

3

Fix the trays

Bolt each letter’s tray onto its studs, with washers and nuts.

4

Wire and test

Run the wiring, solder and seal every joint, switch on.

5

Fit the faces

Slide the trim cap with its acrylic face over each letter.

27-28 February 2026

Trays on, faces on

The letter trays fixed on the parapet with their faces off

Trays first

The letter trays on the wall, faces off, LEDs facing out.

A chemical anchor stud, washer and nut holding the tray to the RCC wall

The anchor

A chemical anchor stud, with washer and nut, holding a tray to the RCC.

Real photos from the installation.

Signed off

A structural engineer checked our work

This was one of the rare jobs where the client asked for a certificate. We brought in an outside structural engineer, who reviewed the fixing method before we started and signed his report after the installation, on 3 March 2026.

His findings, in short: the letters weigh 25 to 30 kg each at most, the 300 mm RCC wall gives the anchors plenty of depth, and the chemically anchored letters are stable and safe for their own weight and for wind, as per IS 875: 2015. Light enough not to harm the wall, and fixed firmly enough not to come down.

Extract from the structural audit report for the Jehangir Hospital sky sign, re-set for the web

An extract from the structural audit report, re-set for the web. The engineer’s name and stamp are not shown.

Wiring a grey weatherproof power box at the foot of the wall: one box for every letter

The wiring

One power supply for every letter

The hospital ran its power cable up to a grey weatherproof box at the foot of the wall, one box for every letter. That was the only part of the wiring on their side.

Inside each box we fitted the letter’s power supply (SMPS), and from there ran our cable through the wall into the letter. So each letter can be switched off on its own: a power supply is swapped at the box, and a faulty LED module can be cut out of its chain and a new one soldered in, without taking the letter down.

One grey power box and power supply for every letter, fed by the hospital’s cable (illustration)

Illustration: the hospital’s cable, our power boxes and our wiring. Not to scale.

Finished

Up close, on the walkway

From the walkway behind the wall you get a sense of the size: the letters stand well above the railing.

The giant J of JEHANGIR from the terrace walkway: white acrylic face, black aluminium sides

The J

The first letter of JEHANGIR, seen along the walkway.

HOSPITAL in 6 ft lit letters along the car park parapet, seen from the walkway

HOSPITAL

The second word running along the parapet.

Real photos of the finished sign.

The sky sign lit at night, seen from the flyover across the road

After dark

Lit every night above the station

From 6 pm, the white faces light up evenly across all sixteen letters, and the name hangs over the station area.

This shot is from the flyover across the road.

HOSPITAL along the parapet at dusk, the Pune skyline behind

HOSPITAL along the parapet at dusk, with the city behind.

Watch

The whole job in five minutes

From the proposal to the workshop, the stairs and the installation: our video of the job.

The specs

What went up

Client

Jehangir Hospital, Pune: the new multi-level car park beside Pune station

When

Planned in 2025; installed 26-28 February 2026

Size

16 letters, each about 6 ft (71.77 in) tall, in a 91 ft line on a 98 ft wall

Letters

3 mm aluminium sides, 4 in deep, riveted; 1 mm aluminium trim cap, 1.5 in deep

Faces

3 mm white acrylic

LEDs

2,105 outdoor-grade Osram modules, 1.8 W each; about 4.2 kW in all

Fixing

Chemical anchors straight into a 300 mm RCC parapet; no frame, no gondola

Checked

Structural engineer’s report: 25-30 kg per letter, safe for dead and wind loads (IS 875: 2015)

Scope

Turnkey: proposal, samples, fabrication, transport, carrying up, installation and wiring (licence by the hospital)

Planning a sky sign?

What it takes, and what it costs

Every sky sign is priced for its building: the height, the wall, how we get the letters up, the size of the letters and the LEDs all change the price. So the price comes with the proposal. Price on request.

Good to know

What to send us

A photo of the building, its height, the wall you have in mind and your name or logo.

The licence

A sky sign needs the municipal corporation’s licence. On this job, the hospital took care of it.

Warranty

Six months from installation, as on all our fabricated signs. The bodies, faces and anchors are built to last for decades.

Running cost

Ask us for the load and units per night, as we worked out for Jehangir.

Read more

More sky signs

Lit signs

Sky signs and 3D LED sign boards

AMJ Land logo and Green’s letters near the top of a residential tower in Pune, by day

All the kinds of lit sign we make, from shop boards to letters for the top of a tower.

See sky signs →

Case study

A sky sign at the top of a tower

The sky sign lit at night, seen from the foot of the tower: the blue AMJ Land logo and the green Green’s letters

Green’s, Thergaon: a block wall, so a steel frame into the beams and a gondola.

Read the AMJ Land story →

Next on this building

The Marathi sign is coming

जहांगीर हॉस्पिटल goes on the other face of the car park later this year, built the same way. We’ll add it here when it’s up.

More signs, high up

Our work

AMJ Land’s Green’s, Thergaon

The whole tower by day, with Green’s near the top

Blue and green lit letters at the top of a residential tower.

See the job →

Our work

Hotel Sahara, SB Road

Hotel Sahara’s lit rooftop sign at night above the hotel on Senapati Bapat Road, Pune

New lit letters on a rooftop sign, readable from a kilometre off.

See the job →

Your turn

Want your name on the skyline?

Send us a photo of your building on WhatsApp. We’ll plan the letters, the fixing and the way up.

Looking for any specific product?

Drop us a line. Send us your query. And we’ll get back to you with solutions and answers.

Mitesh Sanghani, founder of Orchid Digitals
Mitesh Sanghani

Mitesh lives, mostly for Saturdays.

But when forced to work, you’ll find him heading Orchid Digitals – a printing press in Pune.

If it’s an emergency, try looking for him in the hills behind his house. You’ll almost certainly find him… lazing under a tree, with a book in hand.

Latest Products & Blogs

Pune’s Skyline, Seen From Pune Station: How We Built a 91 ft Sky Sign for Jehangir Hospital

How Lit 3D Letters Are Made: A 3D-Printed Letter vs a Channel Letter

LED Neon Set Into Wood: How We Made the Machan Sign for a Children’s Clinic

Share this article
Mitesh Sanghani
Written by
Mitesh Sanghani
Proprietor at Orchid Digitals, Pune. With 20+ years in the printing industry, Mitesh writes about print technology, corporate branding, and signage solutions that help businesses make a lasting impression.
Orchid Digitals, Pune View all posts
Our Location
Email Us
Call Now
WhatsApp